
March 25th: After ground improvement work was completed, waterproof sheeting was laid.

April 1st: Rebar inspection was conducted

The thickness and spacing of the rebars were checked.

April 2nd: Concrete pouring for the foundation slab was completed.

Metal fittings for bolting the columns were also installed.


April 5th: Inspected the lumber processing plant and confirmed the materials
to be used.

April 12th: The roof framing was completed without incident.




April 16th: Regular meeting was held.The temporary toilet was placed as
far away from the neighboring house as possible. I can feel the thoughtfulness
of the construction company here as well. It's important.

April 19th: Scene of the government's structural inspection.

April 19th: The performance of the metal fittings can be determined by
their color.It's convenient for construction and inspection.


1st floor: A spacious area where you can see the south side from the north
side across the courtyard. The carpenters are also working on the base
for the curtain rail. I was surprised that they installed such a solid
base! Good work. Even very thick curtain rails can be installed. If it
were my favorite roller blinds, a base one-quarter of this size would be
fine.

2階子供部屋から見る平屋部分の屋根 横になって寝てみたい屋根です

April 23rd: An emergency on-site meeting was held.There are several things
that need to be decided quickly, so we increased the number of meetings.
April 30th: We discussed how to check the lighting fixtures, switches, and outlets.
On May 14th, we will go to the site and check the location of each outlet, switch, and lighting fixture one by one.

May 5th: I took a picture of the roof.The top is the roof of the second
floor.The bottom is the roof of the first floor. The roofing has been carefully
done so that the excess on both sides is the same. Of course...


May 14th: As planned, we checked the location of the lighting, outlets,
and switches. There were many things that were different from what was
planned in the drawings, and I felt the importance of final confirmation
with the homeowner on site.


May 19th: Site supervision.Confirmed that the insulation material is F☆☆☆☆.
Of course... We also discussed the materials around the doors and windows
with the construction company in advance. We decided to make a proposal
on the 21st.

May 21st: Regular site meeting.The insulation material had been properly
packed into the ceiling space on the second floor. We also checked the
materials around the doors and windows. On this day, the homeowner also
went up to the second floor to check the progress.


Although it is only a 1-tsubo (approx. 3.3 sq m) open space, it feels very
large.I think that is because the space has become truly rich.

June 4th: Regular site meeting. The staircase installation is complete.
Now it is safe to go up to the second floor.

June 9th: Regular site meeting.Trees have been planted in the courtyard.
It is getting nicer and nicer even in places the designer is unaware of.This
is the symbolic tree as seen from the built-in desk in the study/utility
room. It makes living in the home even more enjoyable.

June 18th: Site supervision. The wood deck has finally been installed.
It is a resin wood deck, so no maintenance is required. However, the treatment
of this hole needs to be considered. What if an animal accidentally goes
in?

Handover is in 10 days. The finishing touches are in the final stretch.
June 24th: Government final inspection. The government final inspection
was completed without any problems.

The difference between the top and bottom photos is whether the shutter
in the center is open or closed. I think it's usually closed for security
reasons, but I hope you'll open it occasionally and have garden parties
or something.

June 25th: Client inspection & designer inspection . We spent about
two hours inspecting the water supply and drainage, the condition of the
underfloor area, the condition of the doors and windows and finishes, and
the exterior.
About 10 items of corrective work were required, but I think the client
was satisfied.
June 29th: The completion inspection certificate was issued by the local
government. The handover of the building has been set for July 9th.I hope
everything goes smoothly until the end.I plan to upload the completed photos
separately .
|
|
|
|
 |