
The ground-breaking ceremony was successfully held at the end of February.

There was a gap in time since the ceremony, but the rebar work was carried
out,

The hold-down metal fittings connecting the foundation and base were securely
installed

The roof underlayment work was carried out, with insulation material being fitted between the wooden beams.

The blue material in the background is the insulation material that will
be placed on the roof .

The roof framing was carried out on April 25th


The roof-raising ceremony was held on May 1st.A commemorative photo was
taken with everyone involved.
The spiral staircase was successfully installed.

On May 15th, a structural inspection was conducted by an inspection agency.

The lower metal fittings for the bracing were checked .

The lower metal fittings for the bracing were checked.Tatsumi Co., Ltd.'s
Kletec metal fitting method was adopted.

Recently, metal fittings are also used for the diagonal bracing beams.

Structural plywood was used for the load-bearing walls .The nail pitch
is also an important checkpoint.

Insulation was naturally installed under the first-floor floor .


The client and the construction company were having a regular meeting

The unit bath was installed. Outside the large window is a roof terrace.

Insulation was installed on the exterior walls. The material used is Sunmat
. ☆☆☆☆ Quality, and of course, there is no asbestos.
 Drawing detailed drawings called construction drawings is also an important job for the construction company.
In this case, the construction company created many 1/5 detailed drawings based on the 1/5 detailed drawings presented by the design,
and considered them as the contractor. Such mutual consideration among
the parties involved is important.。


OSB will be used for some of the interior finishes.

The mortar base for the exterior wall of the roof terrace is complete.

A favorite of the designer


屋根ガルバリュウム鋼板葺き
奥のブルーシートは2階ルーフバルコニーを養生しています。
 It was Saturday, but the construction company conducted a safety patrol.
It is very rare for a construction company with around 15 employees to organize subcontractors to conduct safety patrols at each site.
Their high level of safety awareness gives a sense of organizational strength and confidence.


The bedroom is 60 cm higher than the children's room. The view of the first
floor from the children's room also enriches the space.

The ceiling leading from the earthen floor to the LDK is covered with galvalume
corrugated steel sheeting


The joints of the plasterboard base have been puttyed.

The exterior walls have a plaster-like finish

Interior painting work has begun.








The LDK as seen from the entrance earthen floor is almost complete.

LDK

Second floor children's room

Second floor children's room

Instruction manual and warranty set.
Construction completed on August 25th. The new house has been handed over from the builder to the homeowner.
Thank you for your long-term support. However, a long relationship will begin in a different sense. We look forward to working with you.
|
|
|
|
 |