6/18:A groundbreaking ceremony was held on a lucky day. We hope that the
construction will be completed safely.

7/16:Scenes from the earthworks.

7/22:Rebar work for the basement foundation and inspection by the supervisor.On
the same day, an inspection related to the 10-year warranty by the Housing
Guarantee Organization was also conducted.

8月: The concrete structure of the basement's exterior walls and part of
the retaining wall was completed.。

The base reinforcement for the first floor was completed.


September 8th: The
roof-raising ceremony was scheduled for yesterday, a lucky day, but was
postponed to the next lucky day due to the typhoon.However, considering
the construction period, the roof-raising ceremony was held today.It is
always exciting to see everyone's dreams gradually take shape.




△This is the angle from the living room towards the kitchen.Today, it is
still only temporarily fixed with temporary bracing.

△This is the angle from the master bedroom desk corner towards the living room atrium.
 
△9/13, 2004, an auspicious day, the roof-raising ceremony was successfully
held.

△This is the view from the master bedroom's private terrace towards the courtyard.

△View from the rooftop. The rooftop has external insulation. FRP waterproofing
is being considered.
9/17, structural hardware was installed,and seismic structural hardware
such as bracing was checked. On September 21, the intermediate inspection
was also successfully completed.


This month, there were meetings on the 5th, 12th, and 19th.
On the 12th, the client and I checked the electrical outlets. Before attaching
the wall sheathing boards, we check the locations of the main outlets and
switches.
Layout

On the 19th, under the dining room floor.This building uses a foundation
insulation method. Therefore, insulation material is attached to the exterior
walls, including the slab edges.

Thisis a view of the first and second floor walls from the bottom of the
stairs. The glass wool insulation has almost been installed on the walls
of the second floor.

10/29, the Rust Top for the exterior wall underlayment was installed.

11/1, the steel frame of the staircase was installed.
Steel flat bars were assembled quickly by welding.
It will be painted white and wooden treads will be installed.

11/8, the plasterboard for the ceiling underlayment was installed. A projector
will be installed in the square recess in the ceiling of the elevated walkway.

11/15, a fence was installed in front of the terrace on the road side.
The sense of depth of the entire building has become even greater.

12/2, this is the view from the second-floor corridor.

Looking at the atrium from the second-floor Western-style room.

12/7, looking towards the living room from the dining room.




The exterior wall painting (resin atrium) is complete.

Now the work on the exterior garden will begin.
Construction drawings
Once construction begins, many construction drawings are created in addition
to the contract drawings. The following three images are part of the design,
showing detailed drawings of the gate area and an image of the lock.



Detailed drawings and image of the frameless reinforced glass gate and
electric lock.

12/15,the stainless steel frame for the gate was installed according to
the above drawings.



White oak, the symbolic tree.


 |
|
|
|
|
 |