The ground-breaking ceremony was held safely on an auspicious day in June.

Reinforced concrete construction with external insulation and no scaffolding.

Original decorative formwork construction method



Repair of adjacent building after demolition of existing structure



We supervised the pile construction work. The pile locations were confirmed in advance, and the EAZET method was used for the piles.


The key points of supervision were product inspection of the piles and determination of the construction length. In other words, adjustments were made if the actual conditions differed from the pre-construction ground survey data.


Each pile has product information such as steel pipe strength written on it.


After the pile construction was completed, earthworks began.


Simultaneously with the pile construction, a test fabrication of the RC external insulation decorative formwork (scaffold-free) method was carried out at the Yamaguchi factory.


Confirmation inspection of pile locations was carried out


steel plates were welded to the pile heads


foundation reinforcement work was carried ou





reinforcement inspection and intermediate inspection were completed,





foundation concrete was poured
In parallel with the curing of the foundation concrete, we are preparing the custom-made exterior insulation panels for the first-floor exterior walls.

I traveled to Tokuyama City, Yamaguchi Prefecture, to inspect the custom-made exterior insulation panels.


Normally, in reinforced concrete houses, the concrete load during concrete pouring is supported from the outside by formwork and scaffolding pipes.

However, in this case, because the building was constructed right up to the property boundary, there was no space to erect scaffolding or scaffolding pipes.

Therefore, as an alternative, we specially ordered exterior insulation panels with support ribs (straight bulges) as shown above.

These panels serve three purposes: exterior insulation, formwork, and decorative finishing material.



This is a ready-made product, but its basic structure is as described above. Ribs (straight, bulging sections) are added to withstand the weight of the concrete during construction.






This is the foundation covered with insulation.The concrete formwork for the foundation has been removed.



Rebar work for the first-floor slab has been completed .


Rebar inspection and opening position confirmation have been carried out


Concrete pouring for the floor slab was done





On october 10th decorative exterior insulation panels have been installed up to the third floor .

Formwork panel work for the first floor has begunin August.

Following the concrete pouring for the first-floor slab, the erection of the exterior decorative formwork has begun. The decorative formwork that has been delivered is in the foreground of the photo.


These are the metal fittings for installing the decorative formwork. The base is waterproofed with packing and flashing.。





Insulation material has been installed inside the decorative formwork.





This is the decorative formwork on the outside of the first floor.





Rebar inspection of the first-floor walls has been carried out.





The exterior is the decorative formwork that we have shown you many times, but the interior is general plywood formwork





Inspection of the second-floor slab and beam reinforcement has been carried out.


Decorative formwork on the west side .


Concrete pouring is being done today.








After the concrete pouring, I went up to the second floor with the client.


The insulation panels for the second-floor exterior wall are lifted by a crane and set one by one.





Installation of the insulation panels on the second-floor exterior walls is almost complete .


The decorative exterior insulation panels have been installed up to the second floor.The ribs on the surface create a unique, unprecedented design.


September 15th: Inspection of the second-floor wall and column reinforcement. The client also joined us for the inspection.






After completing the reinforcement inspection, formwork was installed for the inside of the second-floor exterior walls and the third-floor slab.


Formwork panel work for the third-floor slab





September 28th: ​​Rebar inspection by the design supervisor and intermediate inspection by a third-party organization completed.



September 28th: ​​A meeting was held to discuss the original design of the system kitchen in between the third-floor slab rebar inspections.


October 2nd: Concrete pouring for the third-floor slab.





October 13th: Decorative exterior insulation panels were installed up to the third floor.


Rebar inspection completed with the client present.


November 13th: Concrete pouring for the rooftop completed .


This is a staircase structure with support on one side. Wooden treads will be placed on top of this.


Window sash installation has begun. Finishing work will begin soon.


Ceiling substructure installation


elevator installation completed


on January 10, 2008 Interior work is progressing smoothly.

February 2008. Construction is nearing completion.

Atelier: Shelves are made of laminated pine, and the floor is made of 30mm thick cedar planks.


Western-style room: The partition does not extend to the ceiling to create a sense of spaciousness.


The refrigerator in the front separates the kitchen and living room.





Concrete cantilevered staircase.


Sitemap
Works
Process

About us
Fukushima
T Res.

Photos
CG
Record

Model
Voice
Enjoy CG



コートハウス(中庭住宅)は実績豊富な大阪の建築家 塚原建築設計室にご相談下さい
塚原建築設計室 公式 日本 建築家 大阪 住宅設計 一級建築士事務所
注文住宅は実績豊富な大阪の建築家 塚原秀典 塚原建築設計室にご相談下さい
大阪 高級食パン 三景屋 みかげや 熟成
Home
Works
Process
About us
Google  Yahoo

アクセスカウンター