The ground-breaking ceremony was successfully completed on March 15th.


Ground improvement work will begin on March 30th. The depth of improvement,improvement material, and improvement method will be key points of on-site supervision.



Rebar work is underway on April 4th .A rebar inspection will be conducted again in two days.


Rebar inspection is on April 6th .





Normally, hold-down hardware with a maximum pull-out force of 30KN is used, but this time special hardware capable of handling 55KN is being used.


It is a safe design while keeping costs down. After the inspection on April 7th ,some rework was required, and all corrective photos are being recorded.


A regular meeting is held on April 22nd .


The roof-raising ceremony will be held at a later date. I ended up chatting with the client for two hours while watching the roof-raising.




May 4th: Meeting with the client. View of the dining kitchen from near the entrance, across the courtyard.


May 15th: Attended the intermediate inspection .An intermediate roof structure inspection was conducted by four parties:a private inspection agency, a defect insurance company, a structural designer, a site supervisor, and the construction company. This was an inspection of structural load-bearing walls and structural hardware.


View of the living room from the back of the kitchen, across the courtyard.The presence of the courtyard makes the space appear spacious.


May 17th: Topping-out ceremony .We thanked the carpenters and craftsmen and prayed for the safety of the construction.


We also received a heartwarming message card with this logo from the client.





May 26th and 31st: Regular site meetings were held.The dining kitchen has finished laying the 30mm thick solid cedar flooring and is currently curing.





June 9th: Detailed discussion with the construction company about the placement of outlets and 7 switches.





June 13th: Exterior view from a distance.The exterior, incorporating the courtyard, looks larger than expected. 。


June 18th: Planted a Japanese cypress tree as part of the client's work.


June 23rd: The kitchen was delivered. I can't wait to unpack it.


June 23rd: Exterior construction has also begun. Handover is scheduled for summer.


June 27th: Built-in TV stand installed.We chose from three designs and discussed the position of the middle shelf in detail.


July 7th: Outdoor wood deck installed. The material is 30mm thick red cedar.It has been painted with preservative paint, and further finishing paint will be applied in the future.


July 7th: Meeting with the client regarding spotlights for planting.


July 7th: Meeting with the client regarding the placement of clothesline hardware.At this stage just before completion, each meeting is very enjoyable.





July 12th: Had a thorough meeting with the client.The placement of the downlights is well-balanced, which is great .





August 3rd: Successfully completed and handed over.


Sitemap
Works
Process

About us
Courtyard
house56

Photos
CG
Record

Model
Voice
Enjoy CG




コートハウス(中庭住宅)は実績豊富な大阪の建築家 塚原建築設計室にご相談下さい
塚原建築設計室 公式 日本 建築家 大阪 住宅設計 一級建築士事務所
注文住宅は実績豊富な大阪の建築家 塚原秀典 塚原建築設計室にご相談下さい
大阪 高級食パン 三景屋 みかげや 熟成
Home
Works
Process
About us
Google  Yahoo  x

アクセスカウンター