The ground-breaking ceremony was successfully completed on March 15th.
 Ground improvement work will begin on March 30th. The depth of improvement,improvement material, and improvement method will be key points of on-site supervision.

Rebar work is underway on April 4th .A rebar inspection will be conducted again in two days.

Rebar inspection is on April 6th .


Normally, hold-down hardware with a maximum pull-out force of 30KN is used,
but this time special hardware capable of handling 55KN is being used.

It is a safe design while keeping costs down. After the inspection on April 7th ,some rework was required, and all corrective photos are being recorded.

A regular meeting is held on April 22nd .

The roof-raising ceremony will be held at a later date. I ended up chatting with the client for two hours while watching the roof-raising.


May 4th: Meeting with the client. View of the dining kitchen from near
the entrance, across the courtyard.

May 15th: Attended the intermediate inspection .An intermediate roof structure inspection was conducted by four parties:a private inspection agency, a defect insurance company, a structural designer, a site supervisor, and the construction company. This was an inspection of structural load-bearing walls and structural hardware.

View of the living room from the back of the kitchen, across the courtyard.The presence of the courtyard makes the space appear spacious.

May 17th: Topping-out ceremony .We thanked the carpenters and craftsmen and prayed for the safety of the construction.

We also received a heartwarming message card with this logo from the client.


May 26th and 31st: Regular site meetings were held.The dining kitchen has finished laying the 30mm thick solid cedar flooring and is currently curing.


June 9th: Detailed discussion with the construction company about the placement of outlets and 7 switches.


June 13th: Exterior view from a distance.The exterior, incorporating the
courtyard, looks larger than expected. 。

June 18th: Planted a Japanese cypress tree as part of the client's work.

June 23rd: The kitchen was delivered. I can't wait to unpack it.

June 23rd: Exterior construction has also begun. Handover is scheduled for summer.

June 27th: Built-in TV stand installed.We chose from three designs and discussed the position of the middle shelf in detail.

July 7th: Outdoor wood deck installed. The material is 30mm thick red cedar.It has been painted with preservative paint, and further finishing paint will be applied in the future.

July 7th: Meeting with the client regarding spotlights for planting.

July 7th: Meeting with the client regarding the placement of clothesline hardware.At this stage just before completion, each meeting is very enjoyable.


July 12th: Had a thorough meeting with the client.The placement of the
downlights is well-balanced, which is great .


August 3rd: Successfully completed and handed over.
|
|
|
|
 |