3/24 Groundbreaking Ceremony The groundbreaking ceremony was successfully completed in early spring, blessed with fine weather .

4/9 ​​Foundation Rebar Inspection We inspected the thickness, pitch, and splice length of the rebars.










4/25 :Foundation Concrete Pouring Completed



4/25: we used a laser surveying instrument to measure the level of the foundation. The error was ±4 mm.






4/28:Topping-Out Ceremony Just like the groundbreaking ceremony,
we were blessed with fine weather today, and the topping-out ceremony was successfully completed.
Thank you to all the craftsmen for your hard work.




5/6: Roof Waterproofing Sheet Installation Completed
The green sheet visible in the background is the waterproofing sheet. Temporary bracing has been installed so far. Over the next week, we will install the bracing and construct the load-bearing walls.




5/9: Roofing Completed with Galvanized Steel Sheets
This is the silver-colored section in the background. The permanent bracing is gradually being added.




▽ 5/9: This is a photo taken looking up at the second-floor living room and balcony from the children's room.



5/12: Intermediate inspection completed.
Confirmation of bracing and hardware positions completed by a private inspection company.




 





5/15: Construction inspection completed by the Japan Housing Guarantee Foundation (10-year warranty system).



5/20: Exterior wall sheathing plywood almost complete.



▽ FRP waterproofing of the 2nd floor deck terrace completed.



▽ Children's room as seen from the 1st floor corridor.



The left side of the corridor connecting the 1st floor children's room and master bedroom is planned to be a wood deck terrace



5/25: Regular site meeting .
Construction scene of the metal siding Galspan for the exterior walls .




6/3: Aluminum shoji screen delivery begins. Before starting the interior finishing work, aluminum shoji screens are installed along with the glass. Double-glazed windows are used throughout the living spaces.This is for condensation prevention and insulation.

6/3: Site supervision .Today, we confirmed the locations of the outlets and switches. (This is unrelated to the photo, but...)


▽This is the designer's favorite photo. It is common to see the living room from a rooftop terrace, but in this house, you see the living room from the roof .Why? It feels different.



▽The roof is a favorite of both the homeowner and the designer. It was such a warm and sunny day today that I couldn't help but lie down and relax. It feels like I have the sky of this residential area all to myself.




6/10: This is a view of the children's room from the back of the first-floor bedroom. The site is used efficiently, giving it considerable depth.



6/17: The baseboards are being installed on the walls of the second-floor living room. Insulation is installed inside the walls, but the roof has external insulation, so there is no insulation in the ceiling space.



6/20: The handrail has been installed on the second-floor balcony. It is made of steel and has been treated with hot-dip galvanizing to prevent rust.



6/24: Installation of the stair treads has begun.The material is laminated ash wood. One month left until handover. Almost on schedule.



7/1: The stucco spraying work on the exterior walls is complete. A fence with cedar planks will be installed on the road side at a later date. The plan is to create a softer look by adding cedar planks to the metal and white walls.  


7/1: Installation of the entrance canopy and stainless steel frame is complete. Weather-resistant transparent polycarbonate sheets will be placed on top of this frame. The design can be done with just one stainless steel support rod. However, the reason for using two is that we believe that even in the event of metal fatigue or some other accident 10 or 20 years from now,both rods will not come off at the same time.



▽ In short, we always consider both design and safety. We also created an image drawing like the one below in advance to discuss the design of the canopy, etc. with the client .



▽Painting of the steel handrail.The handrail has been treated with hot-dip galvanizing, so there is no need to worry about rust.However, it should be noted that when treated with hot-dip galvanizing, general OP paint does not adhere well, and surface preparation for painting is necessary. Also, this time the painting contractor used urethane paint, which dries quickly and gives a nice finish.Faster drying shortens the working time when applying multiple coats, leading to labor cost savings (cost reduction). (Photo taken on 6/30)



▽Painting of the steel handrail.The handrail has been treated with hot-dip galvanizing, so there is no need to worry about rust.However, it should be noted that when treated with hot-dip galvanizing, general OP paint does not adhere well, and surface preparation for painting is necessary. Also, this time the painting contractor used urethane paint, which dries quickly and gives a nice finish.Faster drying shortens the working time when applying multiple coats, leading to labor cost savings (cost reduction). (Photo taken on 6/30)






7/8: Second floor living room baseboard and joint treatment completed The second floor will have a painted finish,but the joints of the non-combustible boards will be smoothed and flattened with tape and putty to prevent cracking.






▽The L-shaped kitchen has been delivered, and the area around the stovetop will be covered with white fire-resistant boards.


▽ A wooden deck is being constructed in the courtyard.


▽The entrance is being tiled. The type of tile was decided after visiting a tile showroom with the homeowner. The placement of the tiles in the entrance will, of course, be specified in the design.

Sitemap
Works
Process

About us
Courtyard
house31

Photos
CG
Record

Plan/Model
Media
Enjoy CG




コートハウス(中庭住宅)は実績豊富な大阪の建築家 塚原建築設計室にご相談下さい
塚原建築設計室 公式 日本 建築家 大阪 住宅設計 一級建築士事務所
注文住宅は実績豊富な大阪の建築家 塚原秀典 塚原建築設計室にご相談下さい
大阪 高級食パン 三景屋 みかげや 熟成
Home
Works
Process
About us
Google  Yahoo

アクセスカウンター
size