Existing building (Photo from Google Maps)
My first impression was that the existing building was quite grand. However,
since it had deteriorated significantly, the client requested to demolish
it and build a new one.

5/10 – The ground-breaking ceremony (Jichinsai) was successfully completed.

2 26 – Conducted deep mixing method for ground improvement (columnar stabilization).
 3/2 – Poured leveling concrete (Sutekon) and confirmed the layout.

3/6 – Rebar inspection.

3/6 – Rebar inspection.

3/15 – Regular site meeting.


3/21 – Roof-raising (Muneage / Framework completion).

3/30 – Regular site meeting.


4/4 – Roof framing and hardware inspection completed.

4/4 – Roof framing and hardware inspection completed.

4/12 – Installed insulation under the first-floor deck.

4/19 – Currently installing cedar flooring (30mm thick) on the second floor.

5/8 – Insulation work for each room is almost complete.

5/11 – Plasterboard installation for the second-floor rooms is about halfway
finished.
 Confirmed the locations of electrical outlets and switches with the client before installing the plasterboard in the first-floor dining/kitchen area.

5/18 – Finished installing the ceiling for the LDK (Living, Dining, and Kitchen) area.


5/25 – Checked the roof; a vent has been installed on the upper ridge.
 6/2 – Completed installing drywall (gypsum board) for the walls and ceiling base.

 6/16 – Applied joint compound (putty) to prep the walls before wallpapering.


6/27 – Cleaning in progress prior to final handover.

6/27 – Cleaning in progress prior to final handover.
|
|
|
|
 |