2 26 ? Conducted deep mixing method for ground improvement (columnar stabilization).

3/2 ? Poured leveling concrete (Sutekon) and confirmed the layout.

3/6 ? Rebar inspection.

3/6 ? Rebar inspection.

3/15 ? Regular site meeting.


3/21 ? Roof-raising (Muneage / Framework completion).

3/30 ? Regular site meeting.


4/4 ? Roof framing and hardware inspection completed.

4/4 ? Roof framing and hardware inspection completed.

4/12 ? Installed insulation under the first-floor deck.

4/19 ? Currently installing cedar flooring (30mm thick) on the second floor.

5/8 ? Insulation work for each room is almost complete.

5/11 ? Plasterboard installation for the second-floor rooms is about halfway
finished.

Confirmed the locations of electrical outlets and switches with the client before installing the plasterboard in the first-floor dining/kitchen area.

5/18 ? Finished installing the ceiling for the LDK (Living, Dining, and Kitchen) area.


5/25 ? Checked the roof; a vent has been installed on the upper ridge.

6/2 ? Completed installing drywall (gypsum board) for the walls and ceiling base.


6/16 ? Applied joint compound (putty) to prep the walls before wallpapering.


6/27 ? Cleaning in progress prior to final handover.

6/27 ? Cleaning in progress prior to final handover.
|