Existing building (Photo from Google Maps)
My first impression was that the existing building was quite grand. However, since it had deteriorated significantly, the client requested to demolish it and build a new one.


5/10 – The ground-breaking ceremony (Jichinsai) was successfully completed.



2 26 – Conducted deep mixing method for ground improvement (columnar stabilization).



3/2 – Poured leveling concrete (Sutekon) and confirmed the layout.




3/6 – Rebar inspection.



3/6 – Rebar inspection.



3/15 – Regular site meeting.







3/21 – Roof-raising (Muneage / Framework completion).



3/30 – Regular site meeting.







4/4 – Roof framing and hardware inspection completed.



4/4 – Roof framing and hardware inspection completed.



4/12 – Installed insulation under the first-floor deck.



4/19 – Currently installing cedar flooring (30mm thick) on the second floor.



5/8 – Insulation work for each room is almost complete.



5/11 – Plasterboard installation for the second-floor rooms is about halfway finished.



Confirmed the locations of electrical outlets and switches with the client before installing the plasterboard in the first-floor dining/kitchen area.



5/18 – Finished installing the ceiling for the LDK (Living, Dining, and Kitchen) area.







5/25 – Checked the roof; a vent has been installed on the upper ridge.



6/2 – Completed installing drywall (gypsum board) for the walls and ceiling base.








6/16 – Applied joint compound (putty) to prep the walls before wallpapering.








6/27 – Cleaning in progress prior to final handover.



6/27 – Cleaning in progress prior to final handover.







Sitemap
Works
Process

About us
Courtyard
house70

Photos
CG
Record

Model
Enjoy CG





コートハウス(中庭住宅)は実績豊富な大阪の建築家 塚原建築設計室にご相談下さい
塚原建築設計室 公式 日本 建築家 大阪 住宅設計 一級建築士事務所
注文住宅は実績豊富な大阪の建築家 塚原秀典 塚原建築設計室にご相談下さい
大阪 高級食パン 三景屋 みかげや 熟成
Home
Works
Process
About us
Google  Yahoo

アクセスカウンター