Groundbreaking ceremony

Columnar soil improvement

Earthwork completed

Foundation reinforcement

Foundation concrete pouring

1st floor, wall reinforcement

1st floor, road-side outer formwork


2nd floor, south side floor and beam reinforcement inspection

2nd floor, north side floor and beam reinforcement inspection

2nd floor, floor and beam concrete pouring

2nd floor ,floor and beam concrete pouring


Steel staircase delivered
It's a very impressive staircase

Check for levelness

2nd floor, wall and column reinforcement inspection


R floor, reinforcement inspection

1st floor, formwork removal




2nd floor, formwork removal also completed

Substrate work begins before painting work


sash work has also begun

Rooftop floor waterproofing Substrate work completed

Glass work and mortar filling around sashes completed

This time it's a painted finish, not exposed concrete. lso, instead of
a sharp corner finish, the corners were repaired with plastering work.

Wiring work begins, at this stage the client confirms the location of the
electrical box.



June: 1st floor subfloor construction begins.

1st floor: Exterior wall spray insulation installation.

2nd floor : Spray insulation installation.

1st floor: Spray insulation installation & subfloor construction.

1st floor: Exterior wall insulation installation, including the ground floor area.

2nd floor: Spray insulation installation & subfloor construction.

Spray insulation installation thickness check: Toothpicks marked at 30mm
are inserted.

Exterior staircase waterproofing undercoat construction.

Ceiling and wall undercoat construction begins.

Ceiling and wall undercoat construction begins.

Ceiling and wall undercoat construction begins.

Northeast side eaves painting completed.

East side 1st floor wall painting completed.

East side 1st floor wall painting completed.

North side roof balcony exterior wall painting completed.

Outdoor staircase painting completed.

Rooftop area painting completed.

Rooftop area painting completed.

Scaffolding removed

Waterproofing paint applied to parts of the exterior that will be partially buried in the soil.

1st floor undercoat boards are almost finished.

Clean stair treads have been prepared separately.

The item in the middle is a washbasin.

2nd floor private rooms also have undercoat boards installed (2022/7/29).




Wallpapering has progressed considerably.



System kitchen installation work,

stair tread installation.