October 22nd Groundbreaking ceremony successfully completed


Ground improvement work


Underground beam reinforcement work Underground


beam reinforcement inspection


Steel frame erection completed


Installation of insulation material under the floor concrete


Floor concrete reinforcement work


2nd floor deck slab reinforcement work





Floor concrete pouring completed


Interior wall base work





Installation of insulation material in the ceiling


Squash court walls Interior insulation material and soundproofing material installation A specification was to prevent the sounds generated by squash and fitness from going outside


An experiment was conducted in advance using the above box to see if the soundproofing conditions were met.The result was that even when the volume was loud enough to damage the amplifier,there was no sound leakage to the outside


Squash court interior wall covering work


Steel painting work started


Steel painting work





Back wall glass door handle installation.A specification was that there should be no handle protrusions on the inside and that it should be easy to lock from both the inside and outside


Court upon completion

Thanks to the cooperation of many people involved, the construction was completed successfully.Thank you very much.

Sitemap
Works
Process

About us
Squash &
Fitness

Photos
CG
Record

'Oli'OliClub
Enjoy CG



コートハウス(中庭住宅)は実績豊富な大阪の建築家 塚原建築設計室にご相談下さい
塚原建築設計室 公式 日本 建築家 大阪 住宅設計 一級建築士事務所
注文住宅は実績豊富な大阪の建築家 塚原秀典 塚原建築設計室にご相談下さい
大阪 高級食パン 三景屋 みかげや 熟成
Home
Works
Process
About us
Google  Yahoo

アクセスカウンター