8/8: On-site supervision of earthwork.
8/9: Layout confirmation was conducted.



8/17: Rebar inspection was conducted.
The type, size, number, and placement of rebars were confirmed.






8/24: The dimensions of the formwork and the location of structural hardware were confirmed.







9/2: The foundation laying was completed.



9/2: The regular on-site meeting was concluded.



9/3: The roof framing was completed. We were caught in the usual evening shower, so we couldn't finish at a good point. We hope that things will proceed smoothly from now on.


9/7: Temporary bracing had not yet been removed at the site, and structural hardware was being installed.


9/13: Notice signs were posted at the site.
It is commendable that the construction company put up clear and large notices for the neighbors. Surprisingly, there are many construction companies that do not take this seriously.


9/13: I went to the site for a legally mandated intermediate inspection.
This involved inspecting the structural walls and hardware. Before the private inspection agency arrived, I double-checked everything, and the inspector, who arrived earlier than scheduled, told me that it was reassuring that I had already checked everything myself. I suppose there are some supervisors who don't do inspections.

On the same day, there were also inspections by the structural designer and the defect liability insurance company. New houses are inspected by four parties.


9/15: We held the roof-raising ceremony.



These days, we don't drink alcohol, but we still had a good time with everyone involved.



9/18: The gate canopy and underlayment are mostly done.




10/7: Exterior siding is being installed .



In the future, a wooden deck will be laid in the courtyard at the same level as the interior floor.


We are currently discussing custom-made furniture at our regular meeting .


October 18th: Underfloor heating is being installed.


The living room has a high ceiling.


10/21: We are installing solar panels with the goal of creating a smart house.






Exterior siding is almost complete.


11/3: The canopy and other parts are coming along nicely.







The eaves gutters aren't as noticeable as I thought, which is a relief.



11/13: Courtyard wood deck underlayment.



November 21st: Hard ipe wood is used for the wood deck.


Checking the placement of stepping stones for the entrance approach with a model.


Viewing the living room atrium from above.



12/2: Entrance approach with exposed aggregate concrete and granite stepping stones.



Original kitchen and backboard designed by the homeowner.


12/2: Open house held.







12/4: Planting trees in the entrance approach.





We are truly grateful to our client.
They visited several other house builders
but ultimately returned to our company.
I believe it was meant to be.
Thank you to everyone involved.







The project was successfully completed and handed over on December 9th.




Sitemap
Works
Process

About us
Courtyard
house90

Photos
CG
Record

Model
Enjoy CG





コートハウス(中庭住宅)は実績豊富な大阪の建築家 塚原建築設計室にご相談下さい
塚原建築設計室 公式 日本 建築家 大阪 住宅設計 一級建築士事務所
注文住宅は実績豊富な大阪の建築家 塚原秀典 塚原建築設計室にご相談下さい
大阪 高級食パン 三景屋 みかげや 熟成
Home
Works
Process
About us
Google  Yahoo

アクセスカウンター